New Construction/Change of Service
For all new construction or existing construction in the YVEA system please call Emma Mortenson at (970) 871-2242.
- For existing construction in the YVEA system please have your service order number available.
- All new construction requires the following documentation prior to a field service representative being assigned to an applicant project:
Pay YVEA Construction Fees
Members have the option to pay their YVEA construction fees online, or by paying cash or check in person at our Steamboat or Craig locations. Please ensure you are selecting the correct fee to pay below. For any questions on which fee to pay, please call Emma Mortenson at (970) 871-2242.
- Engineering Application Fee – $250 Pay Here
Additional Information
Electric Service Requirements Manual
YVEA’s Electric Service Requirement Manual provides applicants, electricians, and existing members with a guide to the expectations for new construction, temporary service, and change of service in YVEA territory. The document should be referenced prior to submitting the New Construction/Change of Service Form.
Engineering Design
YVEA provides a Maximum Available Fault Current Table that satisfies the requirements of the 2017 NEC, Section 110.24. Please reference this table for all engineering design requirements. This table uses the “Infinite Bus” method for calculations with impedances determined by the mean value of YVEA equipment in inventory.
These values may be used to determine a conservative AIC rating for service equipment. YVEA does not recommend or condone using this value for any other electrical purpose, including arc flash analysis. Injury to personnel, including death, and damage to equipment may result. The data is for standard back configurations only, non-standard configuration fault data may be requested through YVEA Engineering.
Arc Flash Analysis
Members may request fault current data to be used for arc flash analysis from YVEA Engineering, which may be subject to an Engineering fee. The analysis required a fault current study to be performed by YVEA Engineering. The data provided from this request is only valid for the system that existed at the time of analysis and during normal system conditions.
The user acknowledges, by acceptance of the data, that the data may change depending on system conditions, future construction, and changes to the member’s service. YVEA does not assume any responsibility for events resulting from the use of this data by the member or any agent of the member.