The system size limits are set by the type of service the member now has or would qualify for with new construction:
- A small service is allowed a system that is capable of producing up to 120% of the member's annual usage or 25 kW, whichever is less
- A medium or large service is allowed a system that is capable of producing up to 120% of the member's annual usage or 150 kW, whichever is less
Facilities larger than those that are specified above would fall outside of our Level 1 or Level 2 fast-tracking process and will require an interconnection study to be completed in order to interconnect with the YVEA system. There are other conditions that may preclude an installation from fast-track processing and these conditions are specified in the YVEA interconnection policy.