What is involved in the inspection process?

Once the DG facility installation is complete, the member or an agent acting on the member’s behalf will contact YVEA Engineering and let us know that the system is ready for inspection. A member-signed (electronic or manual signature) Interconnection Agreement will be sent to YVEA for signature.

The YVEA Approving Authority will coordinate a time and date to test the system to verify anti-islanding capability, the AC disconnect location and operation, the power production of the system, and any voltage rise on the system. As well, there will be a meter exchange with the installation of a net meter, measuring power production as well as consumption. A copy of the completed Interconnection Agreement will be provided to the member or the member’s agent.