What Is Involved in the YVEA Final Inspection Process?

  • Once the installation is complete, the installer will contact YVEA and let us know that the system is ready for inspection. A member-signed (electronic or manual signature) Certificate of Completion will be sent to YVEA for signature.
  • The YVEA Approving Authority will coordinate a time and date to test the system to verify outage monitoring capability, the AC disconnect location and operation, the power production of the system, adequate signage, and any voltage rise on the system.
  • The net meter will be installed which will measure excess power production as well as consumption. A copy of the completed Certificate of Completion will be provided to the member or installer.